5*120 M3 FIRE PREVENTION FLEXIBLE TANKS INSTALLED FOR A SOLAR PANELS FARM

On 27 February 2019
5*120 M3 FIRE PREVENTION FLEXIBLE TANKS INSTALLED FOR A SOLAR PANELS FARM5*120 M3 FIRE PREVENTION FLEXIBLE TANKS INSTALLED FOR A SOLAR PANELS FARM5*120 M3 FIRE PREVENTION FLEXIBLE TANKS INSTALLED FOR A SOLAR PANELS FARM
Pronal have installed 5 fire flexible tanks for our French Partner, manufacturer of solar panels, who needs several fire water systems to fight against fire risks in its sites. Discover here the solution that we proposed to him!

 

As part of French DECI (outdoor fire defense, mandatory upgrading for the companies) our French partner, manufacturer of solar panels needs several fire water systems to fight against fire risks with in its 5 sites. After verification & validation from the French SDIS (fire and secure department service), he has installed a 120m3 tanks on every sites.

Our flexible products have been selected to answer him needs, thank to their good value for money solution, their reliability and their fast implementation in opposition with the rigid solutions.

 

The Flexible tanks complete set

Pronal has provided 5 complete sets including :

· 120m3 fire flexible tanks answering to AFNOR NF S62-250 and NF S65-240 standards

· Hydrants shall, suction application of BAYARD company

· And PVC connecting sets to connect the flexible tank at the hydrant shall

This complete solution helps our partner to make the purchase process easier, as only one supplier will provide him the whole set

 

A simple and quick installation

Here, few civil tasks are required, they only have to think about the water lines frost protection and the creation of the flexible tank platform. Our fire tank is quick and simple to install.

"The flexible tanks is an economical & quick to set up solution that allows us to ensure our site compliance with the anti fire protection regulation. No doubts on their reliability, the flexible tanks have also the advantage to feet to every site specifications. Easy to install, quick to deliver, After sales service easy to reach, we highly recommend PRONAL!" Vincent LEGER from Leger père et fils company.

 

Key figures

5 fire flexible tanks of 120 m3 installed – 2 hours of installation per flexible tank (for 3 persons) – 2 installation days with civil engineering

 

Raw materials

Fire flexible tank – Bayard hydrant shall – Set of PVC connecting

 

Actors

Pronal sales representative:Stephane Gaudiere

Installer:Vincent Léger

  

Vous devez vous aussi installer un point d'eau pour lutter contre les risques d'incendie sur votre lieu de travail ? You need several systems to fight against fire risks in your sites? You need more details  about this project?

You can contact our experts to have more information and be advised by phone:+33(0)3.20.99.75.00 or by email at contact@pronal.com

+33 (0)3 20 99 75 00

Energy sector

Standard or customized range's design of seal, lifting bag, tank, stopper and compensator

Our products